Skip to main content

South Africa | Steel Scrap Shredding Project

Project Overview

South Africa Steel Scrap Shredding and Size Reduction Project

The customer operates a scrap yard where large steel scrap coils, scrap iron blocks, discarded bicycles, and other forms of steel scrap had accumulated over time.

Before the equipment was installed, this material was processed mainly by manual labour. The customer needed approximately 10 workers to carry out the work, resulting in relatively low processing efficiency and high labour costs.

The main objective of the project was to break down large, irregular steel scrap into smaller material while significantly improving on-site processing efficiency and reducing dependence on manual operations.

The customer therefore installed two TSS-800 Single-Shaft Metal Shredders for continuous shredding of large and irregular steel scrap.

South Africa Steel Scrap Shredding and Size Reduction Project
Country / Region
South Africa
Customer Type
Scrap yard
Material
Steel scrap
Typical Materials
Large steel scrap coils, scrap iron blocks, discarded bicycles
Equipment
2 × TSS-800 Single-Shaft Metal Shredders
Project Objective
Reduce steel scrap size, improve processing efficiency, and reduce labour requirements
Recorded Capacity per Machine
Approx. 600–900 kg/h
Key Result
One day of on-site processing after installation was equivalent to approximately one week of the previous manual workload
Manual Processing Was Inefficient for Large, Irregular Steel Scrap
Processing Challenge

Manual Processing Was Inefficient for Large, Irregular Steel Scrap

The steel scrap received at the customer’s site varied considerably in form, including large steel scrap coils, scrap iron blocks, and discarded bicycles.

Because these materials were large and irregular in shape, relying mainly on manual processing required substantial labour and made it difficult to keep up with the growing amount of steel scrap requiring treatment.

01

Wide Variations in Size and Form

The incoming steel scrap varied significantly in size, shape, and structure. Large and irregular pieces required size reduction before they could move into downstream recycling operations.

02

Low Manual Processing Efficiency

Before the project was implemented, approximately 10 workers were required to process the steel scrap. The overall processing rate was not sufficient for the site’s continuous workload.

03

High Labour Costs

Heavy reliance on manual work not only limited the site’s processing capacity but also continued to increase labour costs.

The main challenge was to reliably reduce large, irregular steel scrap to smaller material while increasing the amount that could be handled within a given time.

Processing Approach

Shredding Was Used for Direct Steel Scrap Size Reduction

In this project, the customer did not simply need to reduce the space occupied by loose scrap.

The requirement was to process large and irregular steel scrap directly into smaller material.

Shredding was therefore selected as the main processing route.

The TSS-800 Single-Shaft Metal Shredder uses its cutting system to cut, tear, and shear the incoming steel scrap, progressively reducing the size of the original material and producing smaller metal fragments.

After the project went into operation, the output size was approximately 5 cm, making the material more suitable for subsequent collection, transfer, and recycling.

01Large Steel Scrap Coils / Scrap Iron Blocks / Discarded Bicycles
02Centralized Feeding
03TSS-800 Single-Shaft Shredding
04Cutting, Tearing, and Shearing
05Formation of Smaller Metal Fragments
06Approx. 5 cm Output Size
07Downstream Collection and Recycling
Equipment & Project Configuration

Two TSS-800 Single-Shaft Metal Shredders

The customer installed two TSS-800 Single-Shaft Metal Shredders to process different forms of steel scrap, including large steel scrap coils, scrap iron blocks, and discarded bicycles.

The single-shaft cutting system applies cutting, tearing, and shearing forces to the steel scrap entering the shredding chamber, progressively reducing the size of the original material.

In this project, the main role of the two machines is to improve steel scrap size-reduction efficiency, replace a substantial amount of manual processing with continuous mechanical operation, and produce material within the smaller size range required by the project.

Equipment Type
Single-Shaft Metal Shredder
Model
TSS-800
Quantity
2 units
Material
Steel scrap
Typical Feed Materials
Large steel scrap coils, scrap iron blocks, discarded bicycles
Main Processing Objectives
Size reduction, higher processing efficiency, and lower labour requirements
Output Size
Approx. 5 cm
View Equipment
Two TSS-800 Single-Shaft Metal Shredders
Project Results

Recorded Capacity Reached 600–900 kg/h per Machine, While On-Site Labour Was Reduced from 10 Workers to 3

After the project went into operation, the two TSS-800 shredders took over much of the steel scrap processing work that had previously been carried out manually.

According to operating records, each machine processes approximately 600–900 kg of steel scrap per hour.

With both machines in operation, the amount processed on site in one day was equivalent to approximately one week of the previous manual workload.

At the same time, the number of operators required for the project decreased from approximately 10 to 3.

The shredded steel scrap had an output size of approximately 5 cm, converting the original large and irregular material into smaller fragments.

According to the customer’s project records, the equipment reduced annual labour costs by approximately USD 45,000.

600–900 kg/h

Recorded Capacity per Machine

Each TSS-800 processes approximately 600–900 kg/h of steel scrap in this project.

1 Day ≈ Previous 1 Week

On-Site Processing Efficiency

With both machines operating, one day of processing was equivalent to approximately one week of the previous manual workload.

10 → 3

Operators Required

Mechanical processing significantly reduced the site’s dependence on manual labour.

≈5 cm

Output Size

Large, irregular steel scrap is shredded into smaller material with an output size of approximately 5 cm.

≈USD 45,000 / Year

Labour Cost Savings

According to the project records, annual labour cost savings after equipment installation were approximately USD 45,000.

On-Site Evidence

Customer Site and Processing Results

Related Projects

More Scrap Metal Processing Projects

Related Equipment & Solution

Explore the Equipment and Processing Routes Behind This Project